Imagination Data Centre – London

Imagination Data Centre – London

ICW Powermode were employed to Manufacture, Supply, Install and Commission the complete Low Voltage System.

Working closely with Derry Building Services design team and project managers ensured that special planning , cable routes and bus bar orientation were all developed and finalised prior to any switchgear being installed on site. This included the following items:

  • 3MVA Midel Transformer.
  • 5000 Amp Form 4 Type 6 – 100kA Main LV panel.
  • 5000 Amp Form 4 Type 6 Generator Panel.
  • 1600 Amp Form 4 Type 6 UPS Input/Outputpanels.
  • Four off 800 Amp PDUs with integral Active Harmonic Filters.
  • 3200 Amp Load Bank Connection with VEAM sockets.

Project Details

Project
Imagination Data Centre  – London

Client
Imagination

Main Contractor
Bower & Kirkland

Consultant
AECOM

Electrical Contractor
Derry Building Services

Value
£470K